Vertical Clarifiers with Thickeners
Start Date
December 29, 2021Completion Date
February 28, 2022Location
Pasadena, TXMaterials
All Carbon Steel, Structural Steel, Bar Grating, Heavy PlateFabrication Methods
Rolling, Forming, Beam Line, FCAW Welding, Shop Assembly & Test Fitting
Finishing Details
SP10 Blast, Caulk, Paint System Specifically for Submerged Materials
Size
46’ Long x 30’ Wide x 27’ TallWeight
Filled with water it weighs roughly 616,000# totalSpecial Notes
We had to fully build and erect this in our parking lot. Then we had to completely fill it with about 60,000# gallons of water. The welds were fully inspected by Third Party Inspection and the paint was inspected and tested by a NACE Level II Paint Inspector.
Project Gallery
Project Gallery
Mixing Tank Fabrication
A customer from the water treatment industry approached Swanton Welding & Machining to fabricate a mixing tank assembly. The 50,000 lbs. tank assembly was made up of many different parts and systems including rapid mix, reactor and clarifier tanks, a 16′-8″ long platform, and a 15′ high draft tube. To fabricate these components and many […]
Project Gallery
Discharge Hopper, Clarifier, Clarifier Structure, Catwalk & Stairs, Auger
We custom built a large Discharge Hopper, a Clarifier used to remove slurry, the Clarifier Structure, accessible Catwalk & Stairs, and a custom Auger for the Clarifier. The most interesting thing about this project was its overall size and the custom auger we built.
Project Gallery
Ladle Maintenance Carts
Customer needed a way to conveniently transport large ladles to areas where they will be used.
Project Gallery
Catalytic Converter
Fabricated stainless steel Catalytic Converter w/ Pipe Bundle. A customer approached us about doing this job out of stainless steel with the stainless pipe bundle being made out of a special seamless tubing. The timeline was critical as the customer had a two day plant outage scheduled and they needed this unit installed during that […]
Project Gallery
Project Gallery
125 Ton Steam Car
We built a 125 Ton Steam Car. We fabricated it, blasted and painted it, did the assembly, electrical work, and shop tested it.
Project Gallery
Fulton County Hospital Office Addition
Swanton Welding was tasked with fabricating the steel framework for the new Fulton County Hospital addition in Wauseon, Ohio. We appreciated the opportunity to support Rupp/Rosebrock, Inc. and their construction crews as they constructed a four-story medical building that will attach to Fulton County Hospital. The team at Swanton Welding used our beam line to […]
Project Gallery
Tire Separator and Hopper
The project involved making a hopper & separator for a tire recycling plant. The hopper was designed to dump truckloads of used tires. It has a motor and sliding floor system that was sloped to feed the tires to the separator, which would separate the tires based on size and feed them to additional equipment […]
Project Gallery
CE Boiler Stack Replacement
Swanton Welding was responsible to create a drawing based printed CAD drawings to design and fabricate a replacement stack out of A588 material for the refinery
Project Gallery
Project Gallery
Glass Furnace Rebuild – Support Steel
A client proposed and drew the initial design of this support steel project. It will encase and support a glass melting furnace for the engineered reinforcements industry. Swanton Welding supplied materials such as tie rods, platform steel, stairs, and ladders for the 20 ft tool glass melting furnace. Fabrication, blasting, and painting were customized to […]
Project Gallery
Vertical Clarifiers with Thickeners
These were vertical clarifier tanks used to separate certain materials from water.
Project Gallery
Steel Thrustframe Fabrication
A customer from the gas exploration industry approached Swanton Welding & Machining to fabricate an A36 and A-514 steel thrustframe weldment. The 225,000 lbs weldment was fabricated using a variety of processes, including CNC milling, MIG welding, drilling, laser cutting, bending, tapping and forming. The 54′ long and 8′ wide thrustframe was skillfully fabricated using […]
Project Gallery
4100 Grillage Fabrication
Barge Stabilizer Swanton Welding took on a project with a simple goal: support a 1500 tons crane with two barges. The heavy duty steel frame binding the two barges together, and the crane would be used to drive in bridge pilings.
Project Gallery
Replacement Boom
It is basically the structural arm for a heavy duty conveyor ship loader.
Project Gallery
Accumulator Tower for Metal Coating Process
Structural Steel Tower This project consisted of constructing two similar towers. The entry side is pictured and the exit side can be seen in the distance. This new customer to Swanton Welding requested the project to be finish painted before it was delivered. These structural steel towers were assembled in the field and required very […]
Project Gallery
Truck Dump Project
Swanton Welding fabricated two truck dump platforms. These are used in various industries where semi or other large trucks are driven onto a platform for unloading. After securing the truck, the platform is raised high into the air, and the load on the truck is transferred via gravity into a bin or hopper. Our client builds […]
Project Gallery
Steel Stack Fabrication
Swanton Welding & Machining was approached by a client from the clean air industry to fabricate 950,000 lbs. of steel stacks. Eight large stacks were fabricated using a variety of processes including rolling, bending, forming and MIG welding. The stacks were fabricated using a combination of material such as, A36 steel and 304 and 409 […]
Project Gallery
Industrial Conveyor Fabrication
An agricultural industry client approached Swanton Welding & Machining to fabricate twelve, 5,000 lbs conveyor components. Utilizing AutoCAD 2009, we first drafted complete shop fabrication drawings of the component. We then fabricated the 20′ long, 3’6″ high and 8′ wide conveyor section using a CNC beam line, saws, and drills. After fabrication, during which we […]
Project Gallery
Stainless Steel Hopper
We custom fabricated this stainless steel hopper and finished it off with a polished interior for food grade application.
Project Gallery
Acid Furnace Fabrication
Swanton Welding & Machining was approached by a chemical industry customer to fabricate a 125,000 lbs. acid furnace. We first drafted complete shop fabrication drawings for the furnace using AutoCAD software. We then used a variety of fabrication methods to complete the A516 grade 70 and A-36 grade steel furnace, including: drilling, rolling, laser cutting, […]
Project Gallery
Support Structure
Swanton Welding is fully equipped to meet all your large-scale structural steel project requirements in-house at our cutting-edge USA facility. We take pride in being a dedicated partner in the success of every fabrication project we complete. Recently, we collaborated with a client based in South Carolina to construct a support structure. Given its critical […]
Project Gallery
Bottom Casing for Glass Furnace
This custom fabrication project was for approximately 30 Bottom Casings for a Glass Furnace. Each section had to have pads custom machined to ensure it was within 1 mm of flatness. After the individual casings were completed, we had to shop assemble the entire length of them and use a transit to ensure their critical […]
Project Gallery
Clarifier Tank Project
At Swanton Welding, we have the expertise and resources to meet all your large scale project requirements at our state-of-the-art facility. As your trusted partner in welding and fabrication projects, we are committed to providing exceptional craftsmanship, reliable service, and timely project completion. An example of our capabilities is the recent construction of a sizable […]
Project Gallery
CVG Airport Canopy
Fabrication of two large canopies out of steel tubing to be installed at an airport. The canopies were fully assembled in shop prior to shipping. Both canopies were hot dip galvanized to withstand the corrosive installation environment.
Project Gallery
Purification System Filter
Waste Water Separator This project’s client needed a water tight clarifier tank fabricated. We had to build, weld, leak test, shop assembly, blast, caulk, and paint the tank. In the end, we delivered a completed clarifier tank assembly. Completion Date March 7, 2017 Materials All materials were carbon steel Fabrication Methods This project utilized […]
Project Gallery
Stainless Steel Platform
Custom fabricated stainless structural steel platform with carbon steel columns and handrails.